This project is part of the overall Sewer Bond Issue that was approved by voters in 2008. The Sewer Line Rehabilitation Project will consist of the re-lining of old, deteriorated sewer mains.
During this phase of the project, Ace Pipe Cleaning, of Kansas, City, MO, will be performing inspections and preparatory work to identify problem areas. This work began on June 7, 2010 and will continue through July. This company can be identified with their black and yellow vehicles.
For more information on this project, please call Mike Hightower, mhightower@neoshomo.org or Duane Linch dlinch@neoshomo.org, at 417-451-8081 or City Hall at 417-451-8050.
PROGRESS AS PLANNED